[3.5.2]

3.5.2.  Base Civil Engineering (BCE) prepares SABER program specifications. These include the master specification and the technical or guide specifications. The master specification describes the overall scope of the SABER Program and is part of Section C in the RFP. The technical specifications define specific construction standards for tasks ordered under the contract and form the basis for developing line item work tasks in the UPG. The BCE chooses the UPG after developing the specifications,