3.6.2. Site visit.
The SABER project manager/inspector, contracting officer representative, using organization, and contractor should normally conduct a scope validation/site visit for each project order to discuss topics such as:
3.6.2.1. Site access;
3.6.2.2. Methods and alternatives for accomplishing work;
3.6.2.3. Definition and refinement of requirements;
3.6.2.4. Requirements for plans, sketches, drawings, etc;
3.6.2.5. Detailed scope of work; and
3.6.2.6. Time requirements for completion, phasing requirements, and liquidated damages.