III.  TASK ORDER SPECIFIC INFORMATION

1. Commencement, Prosecution, and Completion of Work (Apr 1984)

The contractor shall be required to: (a) commence work under this contract within _________ [Contracting Officer insert number] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than __________. The time stated for completion shall include final cleanup of the premises.

2.  Notice to Proceed:  The notice to proceed shall be issued within ____ calendar days after award.

3.  Liquidated Damages - Construction (Sep 2000):  (a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of _______________________ [Contracting Officer insert amount] for each calendar day of delay until the work is completed or accepted.  If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

4.  Wage Determination:  The applicable Davis Bacon Wage Determination for this task order is:________________

5.  Payment for Materials Stored on Site:  Payment in advance of installation for materials stored on site will not considered under this task order.

6.  Performance and Payment Bonds:  Performance and payment bonds shall be required within 10 calendar days after award of a task order in accordance with Section H, paragraph 1.28.

7.  Type Task Order:  Firm Fixed Price.

8.  Schedule of Material Submittals:  The submittals contemplated by the FAR 52.236-5, Material and Workmanship, are listed on the attached Schedule of Material Submittals, SAFB Form SMS.

9.  Progress Schedule:  The progress schedule contemplated by FAR 52.236-15, Schedules for Construction Contracts, shall be provided within 5 days after start work.