Procedures for Class J&As
(a) Class justifications and International Agreement Competitive Restrictions (IACR) documents may be used in certain circumstances. For example, they may be used when citing similar justification authority for a group of related contracts for the same or related supplies or services. Each class J&A or IACR must clearly establish for each contract:
(1) The supplies and services that may be acquired;
(2) Contractor(s) and contract type;
(3) The estimated contract value; and
(4) The time period for award and contract performance (including options).
NOTE: Information that is the same for multiple contracts need not be restated for each.
(b) Describe each contract to be approved under a class J&A or IACR as precisely as possible. For replenishment spares, a definite list of stock numbers or part numbers must be included or identified. Additional items cannot be acquired unless an amendment to the J&A or IACR is approved. If the NSN/part number changes due to an ECP, modification, etc., during the effective period of the J&A, a new J&A is not required since these are not new items. The contracting office must maintain a list of all approved items under the J&A or IACR. No parts should be included for which a planned competitive strategy will exist during the term of the J&A or IACR. The J&A should discuss potential for future competition for spare parts included in the list.
(c) All contracts within a class should fall within the same statutory authority. Where a different authority is needed for a contract action, a separate J&A should be prepared.