2.5  Section L Must NOT:

-  Require submission of plans and data with the proposal that are deliverable requirements of the resulting contract unless they are to be evaluated and are necessary for the Source Selection decision.  Request outlines of intended approaches rather than detailed plans, if appropriate.

-  Require offerors to submit items that are intended to be end items of the contract as part of the proposal.  For example, do not require submission of a draft report as part of the proposal if the final report is an end item of the contract.