6.4.3  Cost Summary by Cost Elements

Provide a cost summary by major cost elements by CLIN using the format shown below (and separately identify costs for Other Direct Costs including travel costs):

Table 6.4.3 - Cost Summary by Cost Elements

COST ELEMENT

0001

0002

etc

TOTAL

Prime Hours

 

 

 

 

Inter-divisional hours

 

 

 

 

Subcontractor hours

 

 

 

 

  Total Hours

 

 

 

 

Direct Labor ($)

 

 

 

 

Overhead ($)

 

 

 

 

Material ($)

 

 

 

 

Subcontracts ($)

 

 

 

 

Interdivisional ($)

 

 

 

 

Other Direct Costs ($)

 

 

 

 

  Subtotal ($)

 

 

 

 

G&A ($)

 

 

 

 

  Estimated Cost ($)

 

 

 

 

Facility Capital Cost of Money ($)

 

 

 

 

Profit/Fee ($)

 

 

 

 

  Total Price ($)