5. NEGOTIATION SUMMARY
Price Negotiation Memorandum Checklist | ||||
PNM CONTENTS | PRE | POST | NA | SEE |
5. NEGOTIATION SUMMARY | ||||
a. Discussion/explanation of price analysis performed by the contractor and/or the government's price analysis in the following areas or a statement why it was not performed | ||||
(1) Price element summary for proposed, objective, and considered negotiated amount | ||||
(2) Basis or estimating technique used to determine price reasonableness (attach exemption/waiver if in lieu of cost and pricing data) | ||||
(3) Identify submission of other than cost or pricing data necessary to determine a reasonable price. Include discussion on rationale and required updates (attach sales data, catalogues, competitive price list, independent market prices, other data, etc.) | ||||
(4) Identify subcontractors required to provide cost and pricing data where the prime's requirement has been waived | ||||
(5) Requirement changes and how the price analysis and objective were adjusted | ||||
(6) Significant differences between the objective and negotiated amounts | ||||
(7) Use of advisory information/report to establish the objective, including significant differences between them, the objective, and the final negotiated agreement | ||||
b. Identify proposal of record used to establish objective | ||||
c. When cost and pricing data is obtained, a statement that full reliance was placed on contractor provided data except where specifically identified (including agreed to cut-off dates) | ||||
d. Major cost element summary with sub-paragraph index for proposed, objective and considered negotiated amounts (including direct and indirect costs for labor, materials, etc.) | ||||
e. Discussions/explanations of cost analysis performed for each major cost element for contractor proposed, government objective and negotiated positions in the following areas | ||||
(1) Summary breakout of the components which make up the major cost element amount | ||||
(a) Labor hours by rate category | ||||
(b) Identify and discuss indirect rate | ||||
(c) Materials and other costs by category | ||||
(d) Subcontractor cost or pricing data | ||||
1. Requirement, availability, adequacy, reliance, of subcontractor cost/pricing data | ||||
2. Sole source or competitive | ||||
3. Extent and adequacy of the prime's review | ||||
4. Why certified cost or pricing data not obtained when required (attach - waiver/exemption) | ||||
5. Why certified cost or pricing data obtained when not required | ||||
(e) Basis or estimating method used | ||||
(f) Explanation of contractor data not relied upon and reason for using other than contractor's data, identify data used to develop the government's position (see 5.c) | ||||
(g) Rationale, sources, and currency of the data used to establish the objective (include modification change determined to be non-commercial where originally commercial) | ||||
(h) Requirement changes and how costs were adjusted | ||||
(i) Significant differences between the objective and negotiated amounts | ||||
(j) Actual costs to date, % of completion, trends and, if significant, the contractor's estimate to complete | ||||
(2) With incentive arrangements, describe how the share ratio(s) and ceiling price(s) were established | ||||
(3) When establishing a final price of an incentive contract | ||||
(a) Compare contractor stated costs incurred and acceptable actuals reflected in the objective and explain differences. Show the calculations of the incentive arrangement to adjust the final profit/fee and compare to ceiling price | ||||
(b) Identify significant differences between objective and negotiated position | ||||
(c) Identify supplemental agreements that adjusted targets and state respective amounts | ||||
(d) Identify any firm fixed price and cost reimbursement amounts not subject to the incentive settlement, but which were in the total settlement amount | ||||
(4) Profit. Explain how the objective was developed | ||||
(a) If WGM was used, state assigned weights and provide rationale when weights are below or above normal. (DD 1547 Attach to the PNM) | ||||
(b) If WGM not used, explain why not and how profit objective was developed | ||||