(c) HOW TO BUILD A CANCELLATION CEILING ESTIMATE
(1) The time to build estimates of cancellation ceilings is when you are estimating the cost of the contemplated multi-year contract. Part of that cost estimating process is estimating the cancellation ceiling applicable to each year of the multi-year contract. If possible, the contractor should furnish data points that the cost analyst can use in developing the cancellation-ceiling estimate. This estimate is a Government task, which will require contractor input.
Note: The cancellation ceilings will not be finally established until the multi-year contract is negotiated.
(2) This subsection will take you through eleven (11) steps to develop sound cancellation ceiling estimates.