III. Acquisition Milestones
Include the following: (add additional milestones that may apply and/or exclude those that do not apply to this particular acquisition):
• Acquisition plan approval
• Approval of J&A for other than full and open competition (if necessary)
• Issuance of synopsis
• Request solicitation review (local review, JA review, HQ review/approval)
• Completion of solicitation review/Issue solicitation
• Conduct pre-proposal conference
• Receipt of past performance information/Receipt of proposals
• Begin evaluation of past performance information
• Complete evaluation of past performance information
• Request audit and field pricing support (if necessary)
• Complete discussions if competitive acquisition
• Prepare PPNM if non-competitive acquisition
• Request contract clearance (local review, JA review, HQ review/approval)
• Receive contract clearance /Request Final Proposal Revisions if competitive acquisition
• Receive Final Proposal Revisions if competitive acquisition
• Begin negotiations if non-competitive acquisition
• Complete negotiations if non-competitive acquisition
• Complete FPNM if non-competitive acquisition
• Debriefing prepared
• Contract award
• Conduct debriefings
• Hold pre-preconstruction conference
• Contract start date/contract completion date