4.3.  MACC vs. SABER.

 

MACC

SABER

Contract Type

IDIQ

IDIQ

Ordering

Delivery or task orders

Delivery or task orders

Initial Competition

Competitive

Competitive or set-aside

Program Size

No Limit

Usually $20-$50M over 5 years

Number Contracts

Varies by base but 5-7 provides good competition

Most bases can only support one contract

Competition After Award

- Task orders priced per requirement
- Requirements competed among all awardees

- Task orders priced using commercial unit price books
- No competition unless more than one SABER

Flexibility

Complex projects
Full design & build

-- up to 100% design
-- no restrictions

Non-complex projects
Minimum design

-- up to 35%
-- some updating of old designs

Task Order Scope

$750K-$5M (typical)

$150K-$750K (typical)

Task Order Lead Time

15-45 days average

7-14 days average

Contract Responsiveness - Small requirements

May be less responsive

-- Must compete
-- Longer lead time

May be more responsive

-- If only one contractor
-- Shorter lead time