6.1. Application of DBA.
6.1.1. Should DBA be included in my contract? All contracts in excess of $2,000 issued for construction, alteration, or repair work (including painting and decorating) performed in the 50 United States and District of Columbia on public buildings or public works as defined in FAR 22.401
6.1.2.1. Contract Work Hours and Safety Standards Act (FAR 52.222-4
6.1.2.2 "Approval of Wage Rates" (FAR 52.222-16)
6.1.2.3 "Labor Standards for Construction Work - Facilities Contracts" (FAR 52.222-17)
6.1.2.4. If the contract is for completion of a specific construction project ("build the building", "build the road", etc.) regardless of the amount of time the project will take to complete (i.e. 3 months or 3 years); then a clause to update wage determination(s) and to allow for the adjustment of the contract price are not appropriate or required. However, a Davis-Bacon Act Price Adjustment Clause (
6.1.2.4.1. FAR 52.222-30 "No Adjustment or Separately Specified". Include in: (a) All cost-reimbursement contracts; (b) all fixed-price contracts with a separate pricing mechanism specified (such as a SABER contract using the R.S. Means pricing method); (c) some fixed-price contracts with no other pricing mechanism specified if total contract duration will be 3 years or less (especially if WD rates are not union rates and the WD survey date is less than five years old)*. Consideration should also be given to whether the contractor will be put at substantial economic risk by not allowing for an adjustment to contract price, if DBA wages increase dramatically, or to whether competition is sufficient to moderate out-year pricing escalation by the contractor (e.g. a sole source contract may permit windfall escalation in the out-years).
6.1.2.4.2 FAR 52.222-31 "Percentage Method". Include in: Most fixed-price contracts of any duration, especially contracts involving multiple classifications, where the type of work or total hours are likely to vary significantly from year-to-year, or one or more applicable wage determination rates are union rates (which usually increase every year)*. Using this methodology requires the contracting officer to consider two equally important factors, as follows: (1) what portion of the total contact price should be adjusted? and (2) by what percentage should it be adjusted? The FAR 22.404-12 (c)
6.1.2.4.3 FAR 52.222.32 "Actual Increase Method". Include in: Some fixed-price contracts of any duration involving few classifications, that will be relatively consistent in type of work and total labor hours each year, and wage determination rates for the classifications involved are not union rates (so are likely to change only about once in several years)*. This method may also be appropriate where a sole-source environment may make the "no adjustment" methodology unattractive (since that method may allow the contractor to excessively escalate in the out-years), or where the no adjustment methodology may place a contractor at severe financial risk in the out-years in a highly competitive environment (the contractor may not have escalated at all for the out-year in such circumstances). This method is nearly identical to the Service Contract Act Price Adjustment method required by FAR 52.222-43.
* See the "Davis-Bacon Act Desktop Guide" to learn how to detect wage determination "union dominance" and the survey date (if any or all rates are not union rates).