7.302 Policy.
(S-90) The PM/SM/PL shall examine all options and perform all mission responsibilities and functions using their own resources to the maximum extent practicable.
(S-91) Evaluation. Upon completion of the final Government review of the cost comparison, the HCA makes the final determination for performance by the Government or by a contractor.
(S-92) Upon completion of the public review period and resolution of any questions, the HCA shall provide the CO a written notification of the final cost comparison decision.
(S-93) Appeals. The SPE provides informal administrative review of the initial cost comparison result.
(S-94) The CO shall forward requests to the Director for Procurement (PLD), who will coordinate the review with DISA's Chief Financial Executive (CFE) and the SPE..