5617.7404-3 Definitization Schedule.

(a)

(3)  A request to exceed the limitations of the definitization schedule of an UCA beyond the dates established in DFARS 217.7404-3(a) shall be submitted for approval to the Director of Procurement.

(4)  The request shall include a statement detailing the actions taken to enforce the milestone schedule. If applicable, provide a detailed explanation of any government caused delay or any government action resulting in a substantial contribution to the delay.

HQ, United States Special Operations Command
Special Operations Research, Development, and Acquisition Center (SORDAC-K)
SOFARS 5617
February 2007