SECTION V - SOLICITATION.

Discuss events during the solicitation process.

A.  Pre-bid conferences (FAR 14.207), pre-solicitation conferences (other than Industry Days described in Section III above), pre-construction orientations, or other exchanges with industry before receipt of proposal (FAR 15.201).

B.  How the solicitation was made available.

C.  Questions received and answered.

D.  Amendments issued and resultant changes to acquisition planning.

E.  Protests before closing of the solicitation.

F.  Extent competition solicited and secured. Include information on contractors expressing interest during the solicitation period and offers received in response to the solicitation. If any offerors not submitting a proposal gave an explanation for their decision not to submit a proposal, summarize the explanation. If only one offer was received, explain why the proposal will or will not be considered competitive.

G.  Oral presentations (FAR 15.102). If oral presentations were used, summarize the process including which parts of the proposal were presented orally and participants. Content of oral proposals should be included in sections on evaluation below.

H.  Summary table of proposals. Show a summary table of offerors' prices and ratings/evaluation for each factor required by the solicitation such as technical, past performance, other non-cost factors, and cost. Attachment may be used.