16.603-90 Procedures.

(a)(2)  Requests for HQ DLA preaward review and approval of a letter contract or other undefinitized contract action (UCA) shall be made by the chief of the contracting office. Requests subject to 1.690-6(g) may be transmitted electronically to J-73.

(b)  At a minimum, requests for approval shall include:

(1)  A written Statement of Urgency supporting the requirement for a UCA, including:

(i)  The quantities, dates and priorities of existing and projected requirements to be filled by the buy;

(ii)  The date that the requirement was first known to exist;

(iii)  Why the interests of national defense demand that a contractor be given a binding commitment so that work can begin immediately;

(iv)  Why negotiation of a definitive contract or priced order did not and cannot occur in sufficient time to meet the acquisition need; and

(v)  The determination required by FAR 16.603-3 (letter contracts only) and authorization to take the necessary actions for entering into an UCA required by DFARS 217.7404-1;

(2)  The contracting officer's responsibility determination of the prospective contractor (FAR 9.103);

(3)  The ceiling total price and ceiling unit price(s) to be included in DFARS Clause 252.217-7027 Contract Definitization, an explanation of how they were derived, and documentation of the reasonableness of each ceiling unit price (see 16.703(d)(90) or 17.7603-3(a), as applicable), to include identification of the lowest unit price for each item within the most recent 12-month period.

(4)  The obligated amount, interim billing price, and the predefinitization limits of the Government's liability under the UCA;

(5)  A discussion of any requirement for progress payments, provisional payments, and options for increased quantity or performance period;

(6)  The proposed definitization schedule including dates for--

(i)  Receipt of the contractor's proposal;

(ii)  Beginning of negotiations;

(iii)  Completion of negotiations;

(iv)  Target date for definitization; and

(7)  The following additional milestone dates (unless another contract management activity will definitize):

(i)  Receipt of field pricing report;

(ii)  Receipt of the local price or cost/price analysis; and

(iii)  Submission of the proposed definitive contract and supporting file for HQ DLA review and approval, pursuant to 1.690-6(c)(6).

(8)  The delivery schedule.

(c)  A copy of the signed letter contract shall be forwarded to HQ DLA, ATTN: J-73, within 1 week of execution.