1436.270-2  Part I-The Schedule.

The CO shall prepare the Schedule as follows:

(a)  Section A, Solicitation/contract form. Use SF 1442, Solicitation, Offer, and Award (Construction, Alteration or Repair), as prescribed in FAR 36.701(a).

(b)  Section B, Bid schedule. Bid schedule.

(c)  Section C, Specifications/Drawings. Include specifications and drawings ( See FAR Part 11) or reference other location in the uniform contract format ( e.g. Section J, attachment ___).

(d)  Section D, Packaging and Marking. Not applicable.

(e)  Section E, Inspection and acceptance. Include inspection, acceptance, quality assurance, and reliability requirements ( See FAR Part 46).

(f)  Section F, Deliveries or performance. Include Suspension of Work, Liquidated Damages, Commencement, Prosecution, and Completion of Work, Variation in Quantity clauses ( See FAR Part 12).

(g)  Section G, Contract administration data. Include Contracting Officer's Representative/Technical Representative identification, and any required administration information ( e.g., accounting and appropriation data).

(h)  Section H, Special contract requirements. Include any special contract requirements which are not included in other sections of the uniform contract format.