7.26  REPLACEMENT OF SUB-CONTRACTORS

7.26.1  The Contractor should bear the risk of poor performance of its Sub-Contractors. The Authority should not be disadvantaged by any change in Sub-Contractors so the performance regime should not be interrupted. The Authority should, however, recognise that it should allow the Contractor the right to replace its Sub-Contractors in order to improve performance and avoid termination. To enable it to do so, the Contractor will normally set a stricter termination threshold (or trigger termination earlier in point of time) in its Sub-Contracts than that which applies in the Contract.

7.26.2  However, where there are one or two Sub-Contractors, the Contractor may find it impossible to find a replacement Sub-Contractor where the deductions accrued at Contract level are such that a further very minor default under the Sub-Contract could trigger termination of the Contract. In these circumstances, the Authority should consider whether it should:

•  give relief from termination of the Contract on replacement of that Sub-Contractor for a limited period of time (e.g. two months) during which failures attributable to poor performance of the relevant Services provided by the replacement Sub-Contractor will not result in termination of the Contract. Financial deductions under the Contract should continue to be made for such failures to incentivise proper performance of that contract and to the extent that the performance regime includes any "ratchet" mechanisms for continued poor performance, these should not be relaxed; and/or

•  cancel any warning notices, in so far as they count towards any termination threshold only, accrued by the Contractor under the Contract in relation to the relevant Services provided by the replaced Sub-Contractor on the appointment of the replacement Sub-Contractor.

7.26.3  The Contractor's ability to benefit from the performance relief regime should be limited to twice in the life of the Contract.

7.26.4  As mentioned above, the Authority should not be disadvantaged by the replacement of any Sub-Contractor. Accordingly, the Authority should consider allowing itself the opportunity to approve the identify of any replacement Sub-Contractor if a request is made by the Contractor for temporary relief under the performance regime following the replacement of a Sub-Contractor. This approval right is consistent with the approach taken in the Direct Agreement (see Section 26 (Funders' Direct Agreement)) and similarly, any such approval rights should be limited to matters of technical competence and financial standing.

7.26.5  For Projects where there are a number of Sub-Contractors the Authority should not give this relief as failures attributable to a single Sub-Contractor in these circumstances are less likely to cause accrued penalty points under the Contract to approach termination thresholds.