9.3  EXPIRY OF THE CONTRACT

9.3.1 As the Expiry Date approaches, the Authority's interest in the maintenance of any Asset will become most acute where ownership and use of the physical Assets will (or may) rest with the Authority from expiry. The Contractor's proper management of the maintenance requirements of such physical Assets will be facilitated by the Authority informing the Contractor of its handover requirements as early as possible prior to the Expiry Date. These issues are dealt with in Section 10 (Surveys on Expiry and Termination).