15.4.2  Consequences of Force Majeure

15.4.2.1  On the occurrence of a Force Majeure Event, the parties should consult to attempt to find a way to continue the Project, such as agreeing how it can be reinstated if destroyed (although neither party will be obliged to do this). The solution will depend on the nature of the event and its effects, but may involve altering the service requirement, amending the payment mechanism or even extending the term of the Contract. The required drafting for dealing with the effects of Force Majeure Events is set out in Section 23.3 (Termination on Force Majeure).