5  COMPENSATION EVENTS AND RELIEF EVENTS

5.1  If:

5.1.1  either Party has reason to believe that a Compensation Event has arisen whether the same is also a breach of this Agreement or otherwise or that a Relief Event has arisen; or

5.1.2  the Authority is notified by the Contractor that circumstances constituting a Compensation Event whether the same is also a breach of this Agreement or otherwise or that a Relief Event has or may have arisen,

in either case having or with the potential to have an impact on the Academy, then the Parties shall promptly consult regarding circumstances that give rise to the claim or potential claim and shall discuss whether there has been or may have been a Compensation Event or Relief Event and shall meet frequently thereafter to review information received from the Contractor in connection with the circumstances that give rise to any claim made by the Contractor with a view to considering the evidence provided.

5.2  In the event that a claim is made by the Contractor to which clause 5.1 applies, the Authority shall take due account of all information provided by the Company where the Company may be in whole or in part responsible for the circumstances that give rise to the Compensation Event and the Authority shall use all reasonable endeavours to resist such claim and to require mitigation of the claim where it ought reasonably to do so.