STANDARDISATION OF PF2 CONTRACTS PROVISION | SOURCE OF CHANGE WHERE RELEVANT | EXPLANATION OF HOW PROVISION HAS CHANGED THE SoPC4 POSITION |
|
| |
Policy | Specifies that Authorities should ordinarily warrant title to land which they provide to the project. | |
Market up-date | Specifies that, for property interests, the generally preferred approach is for the Authority to grant a licence to the Contractor which should be co-terminous with the PF2 Contract (unless it is a residual value project) | |
Market up-date | Notes that the approach in housing projects tends to differ from that of other sectors and that DCLG provides detailed guidance on transfers of residual value interests. |