STANDARDISATION OF PF2 CONTRACTS PROVISION | SOURCE OF CHANGE WHERE RELEVANT | EXPLANATION OF HOW PROVISION HAS CHANGED THE SoPC4 POSITION |
|
| |
Policy | New guidance on greater service flexibility. And in particular pre-priced Elective Services which can be moved in or out of the Contract easily without triggering a rerun of the financial model. | |
Section 11.3.1 (Change Protocols) and 11.3.9 (Documentation and Monitoring) |
| The generic pro-forma protocol produced by HMT should be the basis for protocols produced for different sectors. |
Policy | Pre-agreed mechanics and pricing may be specified for some minor maintenance activities. | |
Policy | Particular care needed with regard to the effect a partial closure of facilities or partial termination has on equity return, with different treatments for anticipated and unanticipated changes. | |
Policy | Provision may be needed in change protocol where minor maintenance to be done by Authority or its own contractor. |