STANDARDISATION OF PF2 CONTRACTS PROVISION | SOURCE OF CHANGE WHERE RELEVANT | EXPLANATION OF HOW PROVISION HAS CHANGED THE SoPC4 POSITION |
|
| |
Market up-date | The need for the Authority to indemnify the Contractor when stepping in where the Contractor is not at fault is clarified. | |
Policy | The circumstances where the Authority is entitled to step in have been expanded to include Emergencies. Also the need for the Authority to use Good Industry Practice when it has stepped in (other than on Contractor breach) is added as required drafting. Definitions are inserted of both Emergency and Good Industry Practice. | |
Clarification | Drafting to recognise that step-in where Contractor is not at fault could occur while the building works are still in progress. | |
Clarification | Drafting to recognise that step-in where the Contractor is at fault could occur while the building works are still in progress. | |
Clarification | Authority's rights of access (required drafting) are restated with explanation. |