5.  Contract Management Liaison Structure & Meetings

The purpose of this section is to set out the liaison and management arrangement between the MOD and the Contractor, as opposed to the organisation and management structure of the MOD in section 3 and the Contractor in section 4.

In this section provide details of the structure and hierarchy of liaison arrangements between the Authority and the Contractor from day-to-day planning meetings to annual reviews, including:

•  the role and function of each layer along with the membership of the meeting, who the chairperson is, any standing agenda and the outputs.

•  the informal dispute escalation procedure, prior to any dispute entering formal mediation/arbitration.

•  any regular progress and/or project management reporting requirements including the provision of reports, their purpose, scope and content and the process for any reviews.

An illustration of a Contract Management Structure that also shows the respective MOD and Contractor governance structure is at Appendix 1.