The purpose of this section is to provide key information in a 'look-up table' or a quick reference document, with further explanation and details provided elsewhere in the Operational Contract Management Manual. This section should include all dates, timescales and trigger events expressed in the Contract where: • the MOD has to make a decision (e.g. in respect of payment, acceptance or certification); or • the MOD has to provide GFA; • the Contractor has to deliver or provide an output (e.g. data/information, a report or other deliverable); • the MOD has to review information, data, reports, claims or proposals; • the MOD or the Contractor have to provide each other with formal written notices, plans or proposals; Also include: • All major milestones during the Construction Phase; • The dates on which debt is drawn-down from any 3rd Party Funders; • Any financial reporting dates; • Any dates relating to the renewal of insurance policies; • The dates on which Value For Money Review, Benchmarking/Market Testing activities are due to take place; |