- identify all Contractual outputs required to be delivered by the Contractor (the "Contractor Obligations"), including the delivery by the contractor of all reports (including progress reports), data and information as well as the delivery of goods and services;
- identify all Contractual inputs required to be provided by the Authority (the "Authority Obligations"), including all Government Furnished Assets and all decisions, consents and approvals;
- identify all processes defined in the Contract (the "Contract Processes"), e.g. the process for submitting invoices for milestone payments;
- identify all events of liaison or meetings between the Authority and the Contractor specified in the Contract (the "Liaison Events") and the purpose and scope of each such event;
- all inputs, outputs and activities specified in the Contract should be clearly and unambiguously allocated to either the Authority or the Contractor and must be clearly separable; they cannot be shared or performed jointly (otherwise the roles, responsibilities and obligations of the parties under the Contract is unclear);
- the interface between each of the Authority's and the Contractor's roles, responsibilities and obligations takes place when:
■ the Contractor Obligations are delivered to the Authority by the Contractor;
■ the Authority Obligations are provided by the Authority to the Contractor; or
■ the Contractor and the Authority meet with each other to either inform or consult with one another;