38. Public Sector Comparator. If it has been agreed to release the PSC, (and it generally should be, except in single tender situations or where it might damage the competition), it should be included in the ITN at whatever level of detail has been agreed as striking the optimum balance between private sector need and MOD's negotiating position.
39. Current assets. If the project involves the evolution from, or direct use of, existing assets, an inventory will need to be provided of the equipment, specification and location (as appropriate).
40. Other information. This should be provided as appropriate to making the ITN self-contained. Less critical - or voluminous - supporting information can best be supplied via the data room (see paragraph 22).