67. At Call for Final Tender the acquisition team will require and bidders should ensure submission of the final and complete tender documentation to the required RIBA design stage.
68. For Single Solution approaches where OPP exists, bidders must ensure that tenders meet OPP requirements and are capable of being refined and finalised to meet reserved matter requirements and likely Section 106 and/or Section 278 requirements at DPP stage, whilst being financially robust and affordable.
69. Where there is no OPP, the acquisition team and bidders should ensure that tenders are likely to be acceptable from a planning perspective including likely Section 106 and/or Section 278 requirements at DPP stage whilst being financially robust and affordable.
Call for Final Tender Base Requirements
Elements | Status | MOD PFU Policy |
Design Brief | RIBA Stage D | Advised |
Planning Statement | LPA Adopted | Advised |
Estate / Area Masterplan | n/a [for Single Solution approach] LDF Compliant, not adopted and for reference only [for Different Solution approach] | n/a |
Outline Planning Permission | LPA Approval [for Single Solution approach] n/a [for Different Solution approach] | Discretionary |
Compliant (includes approved deviations) | Required |