| PFI Assurance Issue: | 3. Timescales (timetable and strategy to close & in-service delivery) …to provide assurance that the PFI contract will be (or continues to be) achievable where the plan & timescales proposed are realistic (when allowing for past performance, best practice, available IPT/industry resources & skills and when compared to relevant guidance), and are sufficiently detailed for the project phase identifying all key activities reflecting PFI acquisition processes. | |||||
| Commercial/Financial Assurance Guide Ref: | DE&S Commercial Assurance Guidance: 14. Contractual Process | |||||
| Relevant MOD policy/guidance used as measure for assurance: | Relevant external policy/guidance used as measure for assurance: | |||||
| • [MOD PFU Guidance Note - Negotiation of PFI Projects]17 • [MOD Guidance Note - Tips on using estimates, assumptions & cost inputs when analysing affordability & vfm of PFI projects]18 • AOF guidance |
| |||||
| Evidence Required for each Procurement Phase | ||||||
| All phases: • Project gantt chart or timetable (plan relevant to phase) • Fallback Plan (and trigger points) | ||||||
| Up to Initial Gate: | Up to Market Engagement: | Up to close dialogue and Preferred Bidder appointment: | Up to Main Gate: | Up to Contract Award: | Post Contract Award: | |
|
|
| • Bidders acceptance of agreed timetable • Negotiation timetable/diary with key dates and outline agendas | • Evidence of performance against contract timescales (assets being delivered on time and contract milestones achieved) • Evidence of timescales processing/delivering changes | |||
__________________________________________________________________________________________
17 In draft.
18 To be drafted.