21. Where a change renders existing synthetic training equipment redundant the MOD pricing team should consider whether the contractor would be able to resell or reuse that equipment. Where this is likely, the issue should be raised with the contractor with the aim of securing a reduction in the price of the change to take account of benefit the contractor will receive from the sale or reuse.