22. Some Changes may result in a tangible increase in the residual value, which the contractor will be able to recover at the end of the contract term (or when the Change is removed). Where this is the case, the contractor's price should be reduced by a suitable amount. This will often be the Net Present Value of the residual value of the Change. Finance staff should be consulted for further guidance.