Key facts

 

684

PFI and PPP
contracts in
England within the
scope of the
government's PFI
savings review

 

 

 

£207 bn

remaining unitary
charge on the 684
operational PFI
and PPP projects
(at June 2013)

 

 

 

£1.6 bn

signed savings
reported to
HM Treasury by
departments (at
June 2013)

 

 

£1.3 billion

HM Treasury confidence adjusted estimate of savings in addition to the £1.6 billion of signed savings, which are in the process of being agreed (after allowing for slippage, non-realisation or both).

118

contracts making up the £1.6 billion signed and £1.3 billion pipeline savings reported to HM Treasury.

566

number of contracts that have not yet reported any savings to HM Treasury.