5.5.1  Submission

The Company shall provide the Agency and the Independent Verifier with four (4) printed copies and one (1) electronic copy each of the final detailed engineering designs and plans not later than [•] Days prior to the Required Continuous Construction Date, subject to any agreement of the Parties to submit other designs and plans at a specified period after the Required Continuous Construction Date. These main drawings and technical plans shall include the following:

(a)  final drawings for the general layout of the Project including permanent access roads;

(b)  general and detailed drawings of the Facilities, including all ancillary facilities, structures and civil works;

(c)  final arrangements of plans for the general layout of machineries and equipment; and

(d)  test procedures that meet the requirements for testing provided in Schedule D (Testing and Commissioning).