5.10 Discovered Heritage Resources

If the Company, the EPC Contractor or any subcontractor finds any a fossil, antiquity or other object having artistic, cultural, historic or monetary value or importance discovered on the Site during construction, the Company shall promptly notify the Agency of such discovery and shall take all reasonable steps (including temporary stoppage of work) to prevent its loss or damage. The Company shall also consult with the Agency before incurring any substantial cost in relation to the discovered articles. If the Project Milestone Schedule is affected as a result of any direction given by the Agency, then the Project Milestone Schedule shall be equitably extended. The Company shall be reimbursed for any additional costs reasonably incurred in order to prevent the loss, removal or damage of the discovered articles.