20.2.5 Force Majeure Termination Buy-Out Provisions

Except for termination of this Agreement as a result of an event of loss caused by a Non-Political Force Majeure Event, in case of termination of this Agreement in accordance with the provisions of this Section 20.2 (Termination due to Prolonged Force Majeure Event), the Agency shall purchase from the Company, and the Company shall transfer to the Agency, the Facilities and the Project for the buyout price and following the procedures set forth in Schedule O (Termination Buy-Out and Transfer Provisions).