For the purpose of performing its obligations under Section 5.1 (General Responsibilities of the Company), the Company shall, among other things, have the right to and be responsible for:
(a) calling for tenders and awarding contracts with or without tender subject to the Financing Agreements and the provision on transactions with Affiliates of the Company set forth in Section 12.7 (Transaction with Affiliates);
(b) causing the preparation of the Implementation Plan and approving or rejecting the same;
(c) appointing and removing consultants and professional advisors;
(d) procuring and installing the New ICT Services and Facilities;
(e) hiring, organizing, removing and directing staff to manage and supervise the Project;
(f) entering into contracts for the supply, purchase or lease of materials, equipment and services including the connection to all utilities needed during installation and operation;
(g) taking the necessary measures to protect people and property, avoid unnecessary interference caused by people and equipment, and prevent any other nuisance and unreasonable disturbance; and
(h) doing all other things necessary or desirable for the timely completion of the Project.