5.4.3 Specific Tasks

The Independent Verifier shall carry out all tasks assigned to it under this Agreement, including the following:

(a)  review of and determining whether the Implementation Plan and detailed designs meet the Design and Technical Requirements;

(b)  supervision, monitoring, and inspection of the state and progress of the installation and setup including performance by the LGU of any installation-related obligation under this Agreement;;

(c)  participation in testing and commissioning, and deciding whether the Company should be issued a provisional or final acceptance certificate;

(d)  determination of any time extensions for completing the Project Milestones; and

(e)  submission of reports and analyses that the Agency or the Company may reasonably request.