As shown in Table 2-1 in chapter 1 of this volume, the approving bodies for LGU projects depending on the level of the project cost are the local sanggunian, regional and local development councils and the NEDA Board's Investment Coordination Committee. Box 2-3 summarizes the documents that need to be presented to the sanggunian and regional and local development councils.
Box 2-3: PPP Project Review Requirements for the LDC and Sanggunian |
A. LGU development plan B. Feasibility study C. LDC project evaluation forms i. General information ii. Risk allocation matrix iii. Technical analysis - Location/Site - Plan for implementation - Gender-responsive social/environmental impact assessment iv. Financial analysis - Financial benefits and costs - Financial viability indicators v. Economic analysis - Economic benefits and costs - Economic viability indicators D. ROW acquisition and resettlement plan E. Plans to mitigate negative social and environmental impact, if any F. Endorsement from the Local Chief Executive of the project G. Financing plan |