Tendering, Submission and Receipt of Bids of Solicited Proposals (Option 2)

While the requirements for this step in the procurement process are similar for options 1 and 2, the simultaneous submission of prequalification requirements with the technical and financial proposals shortens the timeline for the tendering, submission and receipt of bids. Table 2-18 presents the tendering, submission, and receipt of bids process vis-à-vis the responsible party and period of action.

Table 2-18: Tendering, Submission and Receipt of Bids Process for Solicited Proposals (Option 2)

Process

Responsible Party

Period of Action

Publish invitation to prequalify and bid

PBAC

Once every week for 3 consecutive weeks in at least 2 newspapers of general circulation and in at least 1 local newspaper of general circulation in the region, province, city, or municipality

Submit qualification documents and bid proposals

Bidder

Within 90 cd from last date of publication

Submit qualification documents and bid proposals for projects costing above PhP300M

Bidder

Within 120 cd from last date of publication

Pre-bid conference for projects costing < PhP300M

PBAC

At least 30 cd before bid submission

Pre-bid conference for projects costing PhP300M up

PBAC

60 to 120 cd before bid submission

Note: cd - Calendar Days