Award of Contract for Solicited Proposals (Option 2)

Table 2-20 summarizes the award of contract process for option 2, vis-à-vis the responsible party and period of action.

Table 2-20: Award of Contract Process for Solicited Proposals (Option 2)

Award of Contract

Responsible Party

Period of Action

Submit recommendation for contract award to LGU head

PBAC

Within 7 cd after completion of evaluation of financial proposal

Approve recommendation for contract award

LGU Head

Within 7 cd after submission of PBAC recommendation

Sign and issue Notice of Award (NOA) to winning bidder indicating contract conditions and requirements for compliance

LGU Head

 

Receive NOA and comply with the contract conditions and requirements

Winning bidder

Within 30 cd after receipt of Notice of Award

Notify winning bidder

LGU Head

Within 7 cd upon receipt of requirements for award

Sign contract

LGU authorized signatory

Within 7 cd from receipt by winning bidder of advice from the LGU of the complied conditions in the NOA

winning bidder

Within 7 cd from receipt of advice from the LGU of the complied conditions in the NOA

Submit original signed copy of the contract to Approving Body

LGU

Within 7 cd after signing

Issue notice to commence implementation

LGU

Not later than 7 cd from the date of contract approval/signing by the LGU Head

Note: cd - Calendar Days

In the event that the winning bidder fails to comply with the documentary requirements of the contract, the LGU may confiscate the bid security unless the latter extends the deadline.