The proposed government administrative center is to be constructed at__________. The prospective bidder is expected to conduct its own ocular inspection and survey of the proposed site to familiarize themselves with it. The bidder is likewise, free to perform all other technical testings that it may find necessary.
Table 3-18: Required Concept Design Documents
Drawing Number | Drawing Title | Drawing Description | Scale |
1 | Site Development Plan | Site plan of the GAC showing the major components (building, parking, setbacks, circulation, orientation, etc.) | 1:500 |
2 | Floor Plans | Floor plan of ground level and typical floor plan of every succeeding floor indicating building dimensions, space planning, circulation, core, fenestrations, floor elevations. etc. | 1:100 |
3 | Building Elevations | Elevation of all sides of the building indicating external building heights, fenestrations, design features, finishes, etc. | 1:100 |
4 | Building Sections | Sections along 2 major axes to show internal building height and vertical space relationships. | 1:100 |
5 | Detail Floor Plans | Floor plan of specific rooms/spaces of interest showing greater detail as needed for clarity. | 1:50 |
6 | Detail Sections/ Elevations | Sections/elevations of specific rooms/spaces of interests showing greater detail as needed for clarity. | 1:50 |
7 | Miscellaneous Details | Detail drawings showing specific architectural features for clarity | 1:30 (variable) |
8 | Outline Technical Specifications | Brief description of materials and construction methods | N/A |
9 | Perspectives | Rendered perspective drawings showing thematic appearance of the facility from different angles, exterior and interior. | N/A |