The prospective bidder shall submit a preliminary, financing plan which identifies the project costs. These costs shall include items below.
Construction cost estimated on a unit cost basis (lump sum and/or cost per square meter) for each of these items:
- demolition and site preparation
- earthworks
- vehicular parking area
- driveway and sidewalk paving
- utilities (drainage, sewerage, water supply, power)
- building shell and core
- building utility systems (electrical, sanitary, mechanical, communications)
- architectural works (exterior and interior)
- landscaping
- elevators
- air-conditioning
- fire protection
- emergency generator
- security and fencing
- professional fees (architectural, engineering, etc.)
- contractor's profit, overhead and mobilization
- value-added tax (VAT) requirements
Operations and maintenance costs for the following items:
- personnel costs for administrative support staff
- supplies and materials