- The Parties shall establish appropriate monitoring and reporting systems to comply with their monitoring and reporting obligations agreed upon and embodied in the Project Report.
The Project Reports shall be prepared and submitted within ____ calendar days after the end of the calendar month to which they apply. Where a Project Report shows that the Project falls below the key performance indicators, the PROPONENT shall state that fact in the report with a full explanation of the reasons for the below-target performance and the steps that it has or will be taking to ensure that performance is improved to meet the standard.