This section presents the target start of implementation and completion. This section may also indicate important milestones the project has or is committed to accomplish (e.g., expected date of availability of the final FS, Investment Coordination Committee approval by a certain date).
Example:
Milestone | Date of Achievement |
Commencement of Transaction Advisory Services | April 2013 |
Submission of Draft FS/O&M Study | October 2013 |
Submission to ICC | November 2013 |
NEDA Board Approval | February 2014 |
Issuance of RFQ | February 2014 |
Issuance of RFP | April 2014 |
Contract Signing with the Private Proponent | December 2014 |