4.3  Land Acquisition and Right-of-Way

(a)  The LGU shall be responsible at its own cost and expense for obtaining all land rights and permanent rights-of-way required to make the Site available for the construction and operation of the Facilities, including, without limitation, temporary rights-of-way to install and construct the Facilities.

(b)  The Company shall assist the LGU, using reasonable efforts, to acquire temporary rights-of-way or construction easements which the Company needs for the construction and operation of the Facilities in addition to those that the LGU may have already obtained on or before the Effective Date.

(c)  The Company shall be responsible for obtaining all other land rights which it needs that have not been acquired pursuant to Section 2.1 (p) and paragraphs (a) and (b) above.