The occurrence of any of the following events shall constitute an "LGU Event of Default":
(a) The Company is ready, willing, and able to perform the Services but the LGU refuses to accept them without justifiable reason or completely obstructs the Company's ability to perform the Services.
(b) The LGU defaults in the payment of any amount due and payable (which amounts are not in dispute) under this Agreement, which amount exceeds the sum of PHP[•] and such default continues unremedied for a period of sixty (60) Days from receipt by the LGU of a notice in writing from the Company of the amount due and payable.
(c) The LGU fails to perform any of its material obligations under this Agreement which prevents or renders it impossible for the Company to perform its own obligations under this Agreement for a continuous period of sixty (60) Days.
(d) There is an expropriation, sequestration or requisition of a material part of the Project assets and/or shares of the Company by the LGU or other Government Authority.
(e) There is a breach by the LGU of Section 18.1 (No Assignment).