For the purpose of performing its obligations under Section 5.1 (Construction Responsibilities of the Company), the Company shall, among other things, have the right to and be responsible for:
(a) calling for tenders and awarding contracts with or without tender subject to the Financing Agreements and the provision on transactions with Affiliates of the Company set forth in Section 12.7 (Transaction with Affiliates);
(b) causing the preparation of final engineering designs and plans and approving or rejecting the same;
(c) appointing and removing consultants and professional advisors;
(d) purchasing and installing the Facilities;
(e) hiring, organizing, removing and directing staff to manage and supervise the Project;
(f) entering into contracts for the supply of materials, equipment and services including the connection to all utilities needed during construction and operation at the Site;
(g) taking the necessary measures to protect people and property, avoid unnecessary interference caused by people and vehicles, minimize traffic, prevent any nuisance and unreasonable noise and disturbance, and ensure that emissions, discharges, and effluents from the Company's construction activities comply with all Legal Requirements; and
(h) doing all other things necessary or desirable for the timely completion of the Facilities.