5.8.1 Occurrence of Delay

If an event occurs that delays the Company:

(f) in completing the detailed engineering designs and plans as required in Section 5.5 (Design, Drawings and Other Documents) [and the Design Timetable];

(g) in completing the Works in accordance with the Schedule 1 (Design and Technical Specifications)[ and Schedule 6 (Works Timetable)]; or

(h) in meeting any of the Project Milestones,

(each, a "Delay"), the Company shall forthwith provide written notice to the Agency of the occurrence and cause of the Delay, its estimate of the financial consequences of the Delay, impact on the Project Milestone Schedule[, Design Timetable and Works Timetable] and actions taken or proposed to be taken to mitigate the effects of the Delay.