URBAN MASS RAIL SYSTEM CONCESSION - SCHEDULES
>
SCHEDULE 9 CONSENTS
>
Part 1. Company Consents
>
1.2 Consents Required for Construction
1.2
Consents
Required for Construction
The Following
Consents
must be obtained within
[
●
]
Days
from
[
●
]
:
More Information
Board of Investments
Department of Labor
Department of Public Works and Highways
Metropolitan Manila Development Authority
Department of Environment and Natural Resources
Philippine Coconut Authority
National Water Resources Board
Philippine Contractors' Accreditation Board
Land Transportation Office
Department of Labor and Employment
Toll Regulatory Board
Air Transportation Office
Bangko Sentral ng Pilipinas
Bureau of Customs
Bureau of Immigration
Other Consents