1.1 General

From the Continuous Construction Date until the Provisional Operations Start Date, the Company shall prepare and submit to the Agency [monthly] reports, in a form acceptable to the Agency, relating to the progress, cost and completion of the Works.

The Company shall include in such reports the following: :

(a) the progress which has been made and is likely to be made in carrying out the Works;

(b) the extent to which difficulties have been encountered in that respect and the likelihood that the Project Milestones will be met, and, if it is not likely to be met, the extent to which it will be exceeded;

(c) the Company's expectations as to the consequences of the Works Timetable not being met and, in each case, its reasons;

(d) information as to any accident, serious injury or fatality occurring during the Works and any claim or action which may be likely to have a material adverse effect on the Project; provided that the information in this subsection (d) must be given to the Agency as soon as reasonably practicable after the occurrence of the event in question; and

(e) information and other assistance as the Agency may reasonably request to comply with the Agency's reporting obligations under any Legal Requirement as it relates to the construction of the Facilities.